
India's Metro Rail Expansion
India's metro rail network is expanding at an unprecedented pace:
- Operational: Delhi, Mumbai, Bangalore, Hyderabad, Chennai, Kolkata, Lucknow, Jaipur, Kochi, Nagpur, Pune, Ahmedabad, and more
- Under Construction: 1,000+ km across 15+ cities
- Planned: 2,000+ km in various stages of approval
Metro rail construction is among the largest urban infrastructure investments — typically ₹250–400 crore per km for elevated corridors and ₹500–800 crore per km for underground sections.
The civil works (viaduct, stations, tunnels) represent 60–70% of total project cost — making metro projects the single largest opportunity for civil EPC contractors in urban India.
VRSIPL's railway infrastructure experience and heavy civil construction capability position it for metro rail civil works — including viaduct foundations, pier construction, and station building works.
Elevated Viaduct Construction
85% of India's new metro corridors are elevated (cheaper and faster than underground). The elevated viaduct consists of:
Foundation:
Bored piles (1000–1200mm dia, 20–35m deep) in urban ground conditions. Typically 2–4 piles per pier, connected by a pile cap. See how bored piles are built and tested.
Pier:
Single or twin circular/rectangular piers (1.5–2.5m dia) rising 8–15m from ground to viaduct level. Cast using climbing formwork.
Pier Cap:
Hammer-head cap supporting the bearings. For twin-pier systems, a portal frame connects the two piers.
Superstructure — The Segmental Viaduct:
Modern metro viaducts use precast segmental construction:
1. Segments (2.5–3.5m long box sections, 50–80 tonnes each) are cast in a dedicated casting yard
2. Match-cast technology ensures perfect fit between adjacent segments
3. Transported to site on multi-axle trailers at night
4. Erected by launching gantry (span-by-span) or balanced cantilever erection
5. Post-tensioned with high-tensile strand cables
6. Grouted for corrosion protection
Typical span:
25–35m between piers. Longer spans (40–50m) used at road crossings.
Production rate:
A well-organized project produces 6–8 segments/day per casting machine and erects one span (8–12 segments) per day per launching gantry.
Metro Station Construction — Elevated and Underground
Elevated Stations:
- Reinforced concrete frame supporting platform level (typically 12–15m above ground)
- Platform length: 140–180m (for 6–8 coach trains)
- Station box: Concourse level (ticketing, security) + platform level + roof
- Architectural finishes: granite/vitrified tile flooring, aluminium cladding, glass facades
- Services: escalators (4–6 per station), lifts (2–4), ventilation, fire suppression
Underground Stations (Cut-and-Cover method):
1. Construct diaphragm walls (800–1200mm thick, 20–35m deep) as station perimeter
2. Excavate inside the diaphragm walls with strutting/anchoring
3. Cast base slab, internal columns, intermediate slabs, and roof slab (bottom-up method)
4. Or: Cast roof slab first, then excavate below it (top-down method — allows road surface restoration early)
5. Typical depth: 15–25m below road level
6. Typical station box: 250m long × 20m wide × 18m deep
Underground Stations (TBM-launched):
- Platform tunnels are larger diameter (6–8m) bored by TBM
- Station caverns are mined using NATM (New Austrian Tunnelling Method)
- Cross-passages connect twin running tunnels
Station construction is the most complex and slowest element — a single underground station can take 3–4 years to complete.
Track Work for Metro Rail
Metro rail track is fundamentally different from mainline railway track:
Ballastless Track (Standard for Metro):
- No ballast — track is directly fixed to a concrete slab (plinth)
- Fastening system: Pandrol clips or direct fixation plates
- Rail: 60 kg/m UIC 60, head-hardened for curve sections
- Gauge: 1676mm (Broad Gauge) for most Indian metros
- Tolerances: ±2mm alignment, ±1mm gauge — far tighter than mainline
Track Slab Construction:
- On viaduct: Cast in-situ M40 track slab (300mm thick) on the box-section deck
- In tunnel: Either cast-in-situ slab or precast floating slab (on resilient pads for vibration isolation)
- Third rail or OHE (Overhead Equipment) installed after track completion
Special Track work:
- Turnouts (points and crossings) at junctions and depot entries
- Scissors crossovers for operational flexibility
- Buffer stops at terminal stations
- Derailment guards on curves
The civil contractor's role extends to track slab construction — the precision concrete platform on which the track system is installed.
FAQ — Metro Rail Construction
Q1: How is a metro rail line built in India?
Most new Indian metro corridors — about 85% — are elevated. The viaduct is built on bored piles with pile caps and piers, topped by precast segmental box girders that are cast in a casting yard, transported to site at night, erected by a launching gantry, post-tensioned and grouted. Underground sections use diaphragm-wall stations built by cut-and-cover (or caverns mined by NATM), with running tunnels bored by TBM. Track is then fixed to a concrete slab, and the whole sequence is controlled to very tight tolerances.
Q2: How much does metro rail construction cost per km in India?
Elevated metro corridors typically cost about ₹250–400 crore per km and underground sections about ₹500–800 crore per km. Civil works — viaduct, stations and tunnels — make up roughly 60–70% of total project cost.
Q3: Why are most metro lines elevated rather than underground?
Elevated construction is cheaper and faster than underground construction. A single underground station can take 3–4 years to complete, and it is the slowest and most complex element of a metro project, which is why about 85% of India's new metro corridors are elevated.
Q4: How fast can a metro viaduct be built?
A well-organised project produces 6–8 precast segments per day per casting machine and erects one span of 8–12 segments per day per launching gantry. Typical spans are 25–35m between piers, with longer spans of 40–50m used at road crossings.
Q5: How many Indian cities have metro rail?
India has 27 cities with approved or operational metro systems, with 1,000+ km under construction across 15+ cities and a further 2,000+ km planned. Operational systems include Delhi, Mumbai, Bangalore, Hyderabad, Chennai, Kolkata, Lucknow, Jaipur, Kochi, Nagpur, Pune and Ahmedabad.
Related Topics
Continue Reading
Related Articles

Railway Line Construction in India — New Lines, Doubling & Gauge Conversion

Pharma Plant Civil Construction in GIDC Gujarat — Site Development to Handover

Choosing an STP Civil Contractor in India — Municipal & Industrial Guide 2026
Our Related Services
VRSIPL Services Covered in This Guide
Start Your Project
Have an Infrastructure Project?
Contact VRSIPL.
48 years of civil EPC delivery across India — WTP, STP, ETP, industrial civil, power plant, roads, and railways. Class-AA Gujarat. ISO 9001 | 14001 | 45001.
